Rooms 4–6 Modernisation

 

reno2Work is progressing well on Block 3 (Rooms 4–6) modernisation. As you can see from the photos, the classrooms have been gutted, the back wall removed, the floor for the extension at the back of the original block has been completed, framing for the walls and roof has begun and the openings framed from the classrooms into the new space.